Banner Instance Upgrade Schedule


ID
Task Name
DurationStartFinishResource Names% Complete
1
Banner Upgrades/Modifications
161 days?Tue 4/17/01Tue 11/27/01 14%
2
Banner 5.1
24 days?Tue 4/17/01Fri 5/18/01 100%
3
DEVL 5.1 upgrade
3 days?Tue 4/17/01Thu 4/19/01 100%
4
UTST 5.1 upgrade
3 days?Tue 4/24/01Thu 4/26/01 100%
5
TRNG 5.1 upgrade
4 days?Tue 5/1/01Fri 5/4/01 100%
6
BPRD 5.1 upgrade
4 days?Tue 5/8/01Fri 5/11/01 100%
7
BTST 5.1 upgrade
4 days?Tue 5/15/01Fri 5/18/01 100%
8
Banner 5.1.1
22 days?Fri 4/20/01Mon 5/21/01 26%
9
DEVL 5.1.1 upgrade
1 day?Fri 4/20/01Fri 4/20/01 100%
10
UTST 5.1.1 upgrade
1 day?Fri 4/27/01Fri 4/27/01 100%
11
5.1.1 User Testing
11 days?Mon 4/30/01Mon 5/14/01 0%
12
Feedback to SCT on 5.1.1
1 day?Tue 5/15/01Tue 5/15/01 90%
13
UTST 5.1 restore
1 day?Mon 5/21/01Mon 5/21/01 100%
14
Banner 5.2
55 days?Mon 7/2/01Fri 9/14/01 0%
15
Upgrade Delivered
1 day?Mon 7/2/01Mon 7/2/01 0%
16
SEED rebuild from Vanilla 5.1 backup
1 day?Mon 7/2/01Mon 7/2/01 0%
17
SEED 5.2 upgrade
8 days?Tue 7/3/01Thu 7/12/01 0%
18
SEED backup (5.2 'vanilla')
1 day?Fri 7/13/01Fri 7/13/01 0%
19      
20
Rebuild SEED from UTST 5.1
1 day?Mon 7/16/01Mon 7/16/01 0%
21
SEED 5.2 install (on top of UTST structure)
3 days?Tue 7/17/01Thu 7/19/01 0%
22
SEED 5.2 backup (with UTST test data)
1 day?Thu 7/19/01Thu 7/19/01 0%
23
SEED 5.2.1/5.2 User Testing
5 days?Mon 7/23/01Fri 7/27/01 0%
24      
25
UTST 5.2 upgrade
4 days?Tue 8/14/01Fri 8/17/01 0%
26
DEVL 5.2 upgrade
3 days?Fri 8/17/01Tue 8/21/01 0%
27
TRNG 5.2 upgrade
3 days?Wed 8/22/01Fri 8/24/01 0%
28
BPRD 5.2 upgrade
4 days?Tue 9/4/01Fri 9/7/01 0%
29
BTST rebuild from BPRD 5.2
1 day?Tue 9/11/01Tue 9/11/01 0%
30
BTRN Create from BPRD at 5.2
3 days?Wed 9/12/01Fri 9/14/01 0%
31
Banner 5.2.1
45 days?Mon 7/16/01Fri 9/14/01 0%
32
Upgrade delivered
1 day?Mon 7/16/01Mon 7/16/01 0%
33      
34
SEED 5.2.1 upgrade
2 days?Fri 7/20/01Mon 7/23/01 0%
35
SEED 5.2.1/5.2 User Testing
5 days?Mon 7/23/01Fri 7/27/01 0%
36
Feedback on 5.2.1 to SCT Due
1 day?Mon 7/30/01Mon 7/30/01 0%
37
SCT rework of 5.2.1 upgrade
4 days?Tue 7/31/01Fri 8/3/01 0%
38
Rebuild SEED from test data backup
1 day?Thu 8/2/01Thu 8/2/01 0%
39
Install re-worked version od 5.2.1
2 days?Mon 8/6/01Tue 8/7/01 0%
40
User testing of Re-worked 5.2.1
3 days?Wed 8/8/01Fri 8/10/01 0%
41
Feedback on 5.2.1 to SCT Due
1 day?Fri 8/10/01Fri 8/10/01 0%
42
SCT 5.2.1 code freeze
1 day?Fri 8/24/01Fri 8/24/01 0%
43
SCT 5.2.1 fail-over code freeze
1 day?Fri 9/14/01Fri 9/14/01 0%
44
Banner InDirect Cost Modification (IDC)
64 days?Wed 8/29/01Mon 11/26/01 0%
45
IDC Modification delivered
1 day?Wed 8/29/01Wed 8/29/01 0%
46
SEED install
3 days?Thu 8/30/01Mon 9/3/01 0%
47
IDC User Testing
9 days?Tue 9/4/01Fri 9/14/01 0%
48
Report back to SCT on IDC
1 day?Fri 9/14/01Fri 9/14/01 0%
49
Recover SEED to 5.2 from test data backup
1 day?Fri 9/21/01Fri 9/21/01 0%
50
Final delivery of IDC
1 day?Fri 9/21/01Fri 9/21/01 0%
51
SEED IDC 2nd delivery install
1 day?Tue 9/25/01Tue 9/25/01 0%
52
SEED IDC final testing
1 day?Fri 9/28/01Fri 9/28/01 0%
53
SEED IDC install
2 days?Fri 10/12/01Mon 10/15/01 0%
54
UTST IDC install
2 days?Thu 10/18/01Fri 10/19/01 0%
55
DEVL IDC install
2 days?Thu 11/1/01Fri 11/2/01 0%
56
TRNG IDC install
2 days?Thu 11/8/01Fri 11/9/01 0%
57
BTRN IDC install
2 days?Wed 11/14/01Thu 11/15/01 0%
58
BPRD IDC install
2 days?Tue 11/20/01Wed 11/21/01 0%
59
BTST IDC install
1 day?Mon 11/26/01Mon 11/26/01 0%
60
Banner 5.3
42 days?Mon 10/1/01Tue 11/27/01 0%
61
Upgrade delivered
1 day?Mon 10/1/01Mon 10/1/01 0%
62
SEED 5.2 'vanilla' recovery
1 day?Mon 10/1/01Mon 10/1/01 0%
63
SEED 5.3 upgrade
8 days?Tue 10/2/01Thu 10/11/01 0%
64
UTST backup
1 day?Mon 10/15/01Mon 10/15/01 0%
65
UTST 5.3 upgrade
4 days?Mon 10/15/01Thu 10/18/01 0%
66
UTST 5.3 testing
5 days?Mon 10/22/01Fri 10/26/01 0%
67
Go/No-go 5.3 decision
1 day?Tue 10/30/01Tue 10/30/01 0%
68
DEVL 5.3 upgrade
3 days?Tue 10/30/01Thu 11/1/01 0%
69
TRNG 5.3 upgrade
3 days?Tue 11/6/01Thu 11/8/01 0%
70
BTRN 5.3 upgrade
4 days?Mon 11/12/01Thu 11/15/01 0%
71
BPRD 5.3 upgrade
3 days?Fri 11/16/01Tue 11/20/01 0%
72
BTST rebuild from BPRD 5.3
1 day?Tue 11/27/01Tue 11/27/01 0%

 

 

Email with comments Last Revised: Monday July 26, 2004 11:01:51 AM